June 21 The prime contractor for exterior siding |
June 21
Beginning of siding removal SE corner |
June 21 |
June 21
Old wooden window removed |
June 21 |
June 21
First new vinyl windows installed |
June 21 |
June 22 |
June 22 |
June 22 |
June 22
Dump truck donated for debris removal |
June 23 |
June 23
Four windows now replaced with vinyl |
June 23 |
June 23 |
June 24 |
June 24 |
June 27 |
June 27 |
June 27
Rounding the southeast corner |
June 30 |
June 30 |
June 30 |
July 05 |
July 05
New weatherproof eaves |
July 07
Stripping south-east corner |
July 07
Preparing south wall of Alter |
July 07
South-east corner with new siding installed |
July 08
Discovered east-side previously refurbished |
July 08
We are delighted the stain glass windows are in excellent condition |
July 08
East-side below stained glass windows |
July 08
Rounding the northeast corner |
July 11
Starting the new siding on the Chapel |
July 12
Chapel corner completed |
July 20
Full height scaffold on eastside |
July 27
Eastside completed with new siding |
July 27
Old siding removed on lower northside |
July 27
Roofing contractor awarded installation of new metal roofing |
July 27
Sample of new Kasselwood metal shingles |
July 27
New roofing started on upper northside |
July 27
New metal shingles on upper northside |
July 28
The installation of the new metal shingles is progressing |
August 02
The new roofing is edging its way up the north slope |
August 03
The new roofing is edging its way up the north slope to the bell tower |
August 04
New siding is now being installed on steeple walls and main door area |
August 10
Northeast corner - scaffold creeps up both sides of the steeple
|
August 10
Steeple scaffold extended to main roof
|
August 15
New wheelchair ramp constructed on south-side of building |
September 13
East side, second floor wall with siding removed and new windows installed |
September 13
East side, second floor wall with new siding and windows installed |
September 30
West tower having new siding and windows installed |
September 30
North roofing has upper main section completed, and chapel in progress |
October 04
The Church Bell is being attached, through the steeple opening, to the crane for removal |
October 04
The Church Bell is being hoisted high before being lowered to the ground |
October 06
The siding is almost completed on the Church tower, and the roofing is started on the South side |
October 10
The siding is completed on the Church tower |
October 14
The front upper roof is complete, and the upper windows are almost complete
|
October 18
The south upper roof is progressing, and the tower roof is almost complete |
|
|