All Saints Parish

Church Building Renovation Project
Click a photo to enlarge



June 21
The prime contractor for exterior siding

June 21
Beginning of siding removal SE corner

June 21

June 21
Old wooden window removed

June 21

June 21
First new vinyl windows installed

June 21

June 22

June 22

June 22

June 22
Dump truck donated for debris removal

June 23

June 23
Four windows now replaced with vinyl

June 23

June 23

June 24

June 24

June 27

June 27

June 27
Rounding the southeast corner

June 30

June 30

June 30

July 05

July 05
New weatherproof eaves

July 07
Stripping south-east corner

July 07
Preparing south wall of Alter

July 07
South-east corner with new siding installed

July 08
Discovered east-side previously refurbished

July 08
We are delighted the stain glass windows are in excellent condition

July 08
East-side below stained glass windows

July 08
Rounding the northeast corner

July 11
Starting the new siding on the Chapel

July 12
Chapel corner completed

July 20
Full height scaffold on eastside

July 27
Eastside completed with new siding

July 27
Old siding removed on lower northside

July 27
Roofing contractor awarded installation of new metal roofing

July 27
Sample of new Kasselwood metal shingles

July 27
New roofing started on upper northside

July 27
New metal shingles on upper northside

July 28
The installation of the new metal shingles is progressing

August 02
The new roofing is edging its way up the north slope

August 03
The new roofing is edging its way up the north slope to the bell tower

August 04
New siding is now being installed on steeple walls and main door area

August 10
Northeast corner - scaffold creeps up both sides of the steeple

August 10
Steeple scaffold extended to main roof

August 15
New wheelchair ramp constructed on south-side of building

September 13
East side, second floor wall with siding removed and new windows installed

September 13
East side, second floor wall with new siding and windows installed

September 30
West tower having new siding and windows installed

September 30
North roofing has upper main section completed, and chapel in progress

October 04
The Church Bell is being attached, through the steeple opening, to the crane for removal

October 04
The Church Bell is being hoisted high before being lowered to the ground

October 06
The siding is almost completed on the Church tower, and the roofing is started on the South side

October 10
The siding is completed on the Church tower

October 14
The front upper roof is complete, and the upper windows are almost complete

October 18
The south upper roof is progressing, and the tower roof is almost complete